Acceleration of Late Work on the Middle Cross Road of the East Sea Island (Mount Aru) Using Microsoft Project with the Precedence Diagram Method (PDM)
DOI:
https://doi.org/10.59890/ijir.v4i7.224Keywords:
Precedence Diagram Method (PDM), Microsoft Project, Fast Tracking, Crashing, Project DelayAbstract
Delays in the implementation of construction projects are one of the problems that can affect the achievement of project completion time targets. In the East Laut Island Central Cross Road Construction Project (Gunung Aru), implementation delays occurred, causing the project completion to deviate from the planned schedule. This study aims to analyze project delays using the Precedence Diagram Method (PDM), identify activities on the critical path, and evaluate the application of Fast Tracking and Crashing methods through simulation using Microsoft Project as an alternative for project acceleration. The research method used is a quantitative method with a case study approach. The research data consists of the planned schedule, realization schedule, inter-activity dependency relationships, and work durations analyzed using Microsoft Project. The analysis was carried out through the preparation of PDM networks, identification of critical paths, Fast Tracking simulation by modifying predecessor relationships, and Crashing simulation by adding overtime working hours to critical activities. The results showed that the planned project schedule duration was 234 calendar days, while the realized schedule became 328 calendar days, resulting in a delay of 94 calendar days. After conducting simulations using the Fast Tracking and Crashing methods, the project duration was successfully reduced back to 234 calendar days, aligning with the planned schedule. The results indicate that the application of both methods is effective in reducing project delays through the optimization of critical path activities using Microsoft Project
References
Agustin, N. S., Nugraha, W. T., & Rihandiar, E. (2025). Percepatan waktu dan efisiensi biaya menggunakan metode fast track dan crash program (Studi kasus: Proyek Jalan Tol Ciawi-Sukabumi Seksi 3). Jurnal Momen Teknik Sipil Suryakancana, 8(2), 84-91.
Aring, A. A., Arsjad, T. T., & Dundu, A. K. T. (2024). Optimalisasi waktu pelaksanaan dengan metode PDM pada proyek pembangunan Puskesmas Bailang Tuminting. TEKNO, 22(87).
Comparative Study of the Fast Track Method with the Crash Program Method in Accelerating Time and Costs. (2024).
Journal of Planning and Research in Civil Engineering.
Dirawan, G. D., Firnawati, Risqiayah, U. H., Nurfadhila, U., Aprianty, D. W., & Ramadhani, N. F. (2025). Critical Path Identification and Time Estimation in Construction: Application of PDM and PERT. Jurnal Sipakatau: Inovasi Pengabdian Masyarakat.
Ervianto, W. I. (2005). Manajemen Proyek Konstruksi. Yogyakarta: Andi Offset.
Faathir, F. T. (2024). Analisis perbandingan aplikasi program Microsoft Project dan metode CPM dalam penjadwalan proyek konstruksi. Jurnal Pilar Teknologi, 9(1), 8-21.
Husen, A. (2011). Manajemen Proyek: Perencanaan, Penjadwalan, dan Pengendalian Proyek. Yogyakarta: Andi.
Kamalin, H., & Suryanto, M. (2025). Rescheduling of the Hospital As Sakinah Medika Sidoarjo Building Construction Project Using MS. Project. Jurnal Rekayasa Teknik Sipil, 14(1), 162-166.
Lengkong, S. A., Arsjad, T. T., & Malingkas, G. Y. (2023). Analisis penjadwalan proyek menggunakan metode PDM dengan menggunakan konsep cadangan waktu pada proyek pembangunan Balai Kesehatan Ibu dan Anak Kota Manado. TEKNO, 21(84).
Luthan, P. L. A., & Syafriandi. (2017). Manajemen Konstruksi dengan Aplikasi Microsoft Project (1st ed.). Penerbit ANDI.
Mewengkang, D. H., Sumanti, F. P. Y., & Malingkas, G. Y. (2023). Analisis penjadwalan proyek menggunakan metode PDM dengan menggunakan konsep cadangan waktu pada proyek pembangunan Rumah Susun Kejaksaan Tinggi Sulawesi Utara. TEKNO, 21(83), 270-280.
Schwalbe, Kathy. (2019). Information Technology Project Management. Boston: Cengage Learning.
Setyawan, A. A. V., Sundari, T., Yulianto, T., & Nugroho, M. W. (2024). Analisis penjadwalan waktu proyek Gedung Puskesmas Ngoro Kabupaten Jombang dengan menggunakan metode PDM (Precedence Diagram Method). Konstruksi: Publikasi Ilmu Teknik, Perencanaan Tata Ruang dan Teknik Sipil, 3(1), 1-8.
Soeharto, I. (1999). Manajemen Proyek dari Konseptual Sampai Operasional. Jakarta: Erlangga.
Wardana, Z. R., & Putra, I. N. D. P. (2023). Analisis percepatan proyek menggunakan metode fast track dan metode crashing pada proyek pembangunan gedung bertingkat. CIVED, 10(2).
Zuhriyah, A., & Oetomo, W. (2022/2023). Analisis percepatan waktu dengan metode fast track dan crashing pada proyek PT Graynenda Putra Karya. Jurnal Kacapuri: Jurnal Keilmuan Teknik Sipil.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Futri Ellys, H. Muhammad Humaidi

This work is licensed under a Creative Commons Attribution 4.0 International License.