Analysis of Heavy Equipment Cost and Productivity Budget in the Hayupi Road Reconstruction Project, Banjar Regency
DOI:
https://doi.org/10.59890/ijir.v4i7.225Keywords:
Heavy Equipment Productivity, Operational Budget Cost, Schedule Optimization, Combined Capacity, Bottleneck Analysis, Road ReconstructionAbstract
Road reconstruction projects in rural and hilly terrain frequently encounter schedule delay challenges, leading directly to substantial operational cost overruns. A primary driver of discrepancies between planning and field execution is the inaccurate estimation of heavy equipment operational productivity and inappropriate fleet combinations. This study aims to analyze the actual working productivity of heavy equipment, calculate the precise operational budget costs, and formulate schedule optimization strategies for the Hayupi Road Reconstruction Project in Banjar Regency, South Kalimantan. The analytical methodology complies with PUPR Ministerial Regulation No. 1/2022 and No. 8/2023. Hourly production capacity evaluations incorporate cycle times, equipment efficiency factors, and local material parameters. Duration optimization is conducted using the Minimum Combined Production Capacity approach (bottleneck analysis). Secondary data were collected from project technical documentation, including the Bill of Quantities (BoQ), heavy equipment technical specifications, unit prices for fuel/ lubricants, labor wages, and planned S-Curves. The findings indicate that completing the five evaluated core work items (site clearing, common excavation, rock excavation, common embankment from excavation, and aggregate base Class A) requires a rental fleet combination of 3 Excavators, 7 Dump Trucks, 4 Rock Drill Breakers, 1 Bulldozer, 1 Motor Grader, and 1 Vibratory Roller. The total operational budget cost for heavy equipment across these five items is calculated at IDR 4,642,172,450.00
References
Banjar, P. R. (2025). Bill of Quantity (BoQ) dan Rencana Anggaran Biaya (RAB) Proyek Rekonstruksi Jalan Hayupi. Banjarmasin: Pemerintah Kabupaten Banjar.
Banjar, P. R. (2025). Time Schedule (TS) dan Kurva S Rekonstruksi Proyek Jalan Hayupi. Banjarmasin: Pemerintah Kabupaten Banjar.
Burhanudin, B., Syahrudin, S., & M. Nuh, S. (2024). Analisis optimalisasi produktivitas dan kinerja penggunaan alat berat pada proyek peningkatan jalan Pandan-Merarai. Jurnal Elastisitas, 12(1), 45-58.
Faradilla. (2018). Percepatan durasi proyek struktur dengan metode CPM (Critical Path Method). Jurnal Konstruksi Politeknik, 5(2), 112-124.
Muammar, R., & Iqbal. (2025). Analisis produktivitas alat berat pada proyek peningkatan/rekonstruksi jalan rel Kota Langsa. Jurnal Sains dan Teknologi, 14(1), 33-42.
Pradana, R. A., & Winarto, F. E. (2025). Analisa pengaruh produktivitas alat berat dan pembuatan sistem monitoring terhadap BPP proyek.
Jurnal Teknik Sipil & Manajemen, 9(3), 201-215.
Rakyat, K. P. (2022). Peraturan Menteri PUPR Nomor 1 Tahun 2022 tentang Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat. Jakarta: Kementerian PUPR.
Rakyat, K. P. (2023). Peraturan Menteri PUPR Nomor 8 Tahun 2023 tentang Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi.
Jakarta: Kementerian PUPR.
Soeharto, I. (1995). Manajemen Proyek: Dari Konseptual Sampai Operasional. Jakarta: Penerbit Erlangga.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Ahmad Jabar Albanjari, H. Muhammad Humaid

This work is licensed under a Creative Commons Attribution 4.0 International License.