Optimization of Total Project Cost for the Cintapuri Banua Hanyar Road and Bridge Reconstruction Project Using Microsoft Project Through Time-Cost Trade-Off Analysis

Authors

  • Kanniya Muthia Fatmawati Politeknik Negeri Banjarmasin
  • H. Muhammad Humaidi Politeknik Negeri Banjarmasin
  • Hendri Yani Saputra Politeknik Negeri Banjarmasin

DOI:

https://doi.org/10.59890/ijir.v4i7.228

Keywords:

Cost and Time Control, Microsoft Project, Earned Value Method, Rescheduling, Road Reconstruction

Abstract

The success of a construction project is strongly influenced by the effectiveness of time and cost management. The Cintapuri Banua Hanyar Road and Bridge Reconstruction Project has a planned duration of 150 calendar days with a contract value of IDR 6,600,822,000.00. This study aims to determine the optimal duration and cost through Time Cost Trade Off (TCTO) analysis assisted by Microsoft Project 2021 software. The study begins by identifying the critical path of the project including mobilization, temporary bridges, traffic management, earthworks, and road pavement works. Acceleration analysis (crashing) was conducted through overtime work scenarios of 1, 2, and 3 hours on critical path activities. Analysis parameters include calculations of crash duration, crash cost, and cost slope. The results showed that project duration acceleration could be achieved to 140.44 days (1-hour overtime), 134.36 days (2-hour overtime), and 132.75 days (3-hour overtime). Additional working hours increased project costs due to overtime wages and equipment operational costs. Based on the Cost-Time Ratio analysis and time-cost equilibrium, the 2-hour overtime alternative is the most optimal choice with the lowest cost-time ratio of IDR 225,040,629.90 per accelerated day and saving 15.64 days of execution time

References

Badan Standardisasi Nasional. (2023). SNI 1725:2023 Pembebanan untuk Jembatan. Jakarta: BSN.

Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2023).

Spesifikasi Umum Bina Marga 2023 untuk Pekerjaan

Konstruksi Jalan dan Jembatan. Jakarta: Direktorat Jenderal Bina Marga.

Luthan, P. L., & Syafriandi. (2019). Aplikasi Microsoft Project untuk Penjadwalan Kerja Proyek Teknik Sipil. Yogyakarta: Andi Offset.

Priyo, M., & Paridi, A. (2018). Analisis Optimasi Waktu dan Biaya Proyek Konstruksi Menggunakan Metode Time Cost Trade Off. Jurnal Teknik Sipil & Perencanaan, 20(2), 85–94.

Priyo, M., & Sumanto, A. (2016). Analisis percepatan waktu dan biaya proyek konstruksi dengan penambahan jam kerja (lembur) menggunakan metode Time Cost Trade Off. Semesta Teknika, 19(1), 1–15.

Soeharto, I. (1999). Manajemen Proyek: Dari Konseptual Sampai Operasional, Jilid 1 (Edisi ke-2). Jakarta: Erlangga.